SMED Continuous Industry
SMED Continuous Industry
Key Project Objectives
- To make change processes more flexible with the aim of reducing the plant's lead time in its strategic product line.
- Train staff on continuous improvement concepts & Involve staff in every stage of the re-engineering process of change
- Introduce the concepts of 5S, Ergonomics, SMED and Parallel Work
- Create a reporting program that allows you to store and monitor the results.
- Form an internal team for the management & execution of SMED projects
Methodology & Action Summary in 7 Steps
Step 1: Educate to change / open minds
Step 2: Classify / Eliminate variability
2.1 Define the Key Products
Reduction from 25 to 20 Key Products by eliminating products with low or zero production levels in 2012.
2.2 Create Change Class Matrix
Step 3: Define the Starting Point: Where are we?
Step 4: Improve the work environment
Step 5: Democratic Re-Engineering
Step 6: Monitor & Capitalize on Improvements
Step 7: Technical & Functional Improvements
- Elimination of the need for “Sprays” & Independence with Maintenance
- Mechanical Improvement of the Villars Machine
- Electrical Upgrade of the Villars Machine
Lean Change C2 Observations: White ->
- Creation of a dust deviation control program & Independence with production managers
- Control of those in charge through Reporting
- Control of those in charge through supervision of external tasks
Lean Change C2 Observations: White->White with Spray: 54 minutes
White with Spray
Process Re-Engineering Summary
Number of optimized processes
- 66% of the changes observed, defined and optimized
- 34% of the improved changes
Process Re-Engineering Summary
Output1 Output2 Output3 C1 Previous External Tasks Work sequence with 2 PAX External tasks post-change C2 Previous External Tasks Work sequence with 2 PAX External tasks post-change C3 Previous External Tasks Work sequence with 2 PAX External tasks post-change C4 Previous External Tasks Work sequence with 2 PAX External tasks post-change C5 Previous External Tasks Work sequence with 2 PAX External tasks post-change C6 Previous External Tasks Work sequence with 2 PAX External tasks post-change Process dossier
Summary of Actions Taken & Pending
5S Actions: Order / Cleanliness / Safety
| State | Compliance | % | ||||
| Plan | 28 | 100% | ||||
| EARRINGS | 17 | 60% | ||||
| Act / Implemented | 5 | 19% | ||||
| Discarded | 6 | 21% |
7S Actions: Ergonomics / Displacements
| State | Compliance | % |
| Plan | 52 | 100% |
| EARRINGS | 5 | 10% |
| Act / Implemented | 39 | 75% |
| Discarded | 8 | 15% |
Organizational Actions
- Creation of the process dossier
- Operator training
- Definition of external work
- Definition of Objectives
Functional Actions
- Creation of the powder weight program
- Training of those in charge
- Creation of communication & reporting panels
Pending points
Using the powder weight program:
Control of actual weight deviation vs. target / Tray weight deviation / Digital adjustment
Outsourcing the assistant's work:
Having an additional easel for the start of production
Project Results
Analysis of the initial results regarding the implementation period
Coating Trends 2012 1
Evolution of changes C1 White->White
Short-term objectives for the C2 White->White Bi-Co changes.
Short-term objectives for the C3 White->White with Film changes
Short-term objectives for the C5 Black->Black changes
Summary of Results FROM 2/01/2013 TO 17/01/2013
Coating Efficiency January 2013
Short-term future
Now we can start improving!
Improvements applicable to all changes
Monitoring Results / Supporting and Motivating Operators
- Daily review with the operators of changeover times and problems encountered.
- Weekly review with the production manager of changeover times.
- Weekly review of continuous improvement action plans and ongoing actions
Other opportunities for improvement
Quality controls
Today, during each type change, we have several sources of waste due to the current strict quality control process:
- Allow uninterrupted production in cases where the production preparation process is controlled
- Analyze uncontrolled production preparation processes
- Having a quality control indicator on the production line
Evaluation of potential material savings with a process change
production start-up